PRANA / February 2019

Payment Schedule

 

Application/Booking Money10% of Total Price (TP)
On Agreement  – within 30 days of Application / Booking10% of Total Price + 50% Legal Fees + GST
On Completion of Foundation of the Block10% of Total Price
On Completion of Ground Floor of the Block10% of Total Price
On Completion of 1st Floor Slab Casting10% of Total Price
On Completion of 3rd Floor Slab Casting10% of Total Price
On Completion of 5th Floor Slab Casting10% of Total Price
On Completion of 7th Floor Slab Casting5% of Total Price + Electrical & Generator Charges + GST
On Completion of Internal wall finishing of the respective flat booked5% of Total Price + Recreational Facility Charges + GST
On Completion of Flooring of the respective flat booked5% of Total Price + 50% Legal Fees + GST
On Completion of Sanitation /Piping of the respective flat booked5% of Total Price
On Installation of Lifts5% of Total Price
On Possession5% of Total Price + Maintenance Deposit

*TP – Total Price is “Value of the Apartment + Parking Charges”

Note
  • GST applicable as per Government norms.
  • Cheque bounce charges – Rs. 500/- per instrument